N. Pacific, 4th Av, Oak St, and 5th Av

Printer-friendly versionPDF version
Project Area Plan

Project Area Map

Replacement of old, failed sanitary sewer, storm drain, and waterlines, and then repaving of the streets is planned for N. Pacific Av from Cowlitz Way to Allen St, 4th Av from Allen St to Oak St, Oak St from 4th to the east end, and 5th Av from Allen St to Oak St. In addition, sidewalk access ramps will be reconstructed at most corners.

The project is funded by the Transportation Improvement Board, as part of the Arterial Preservation Program, and the City of Kelso.

Project Schedule:

Design and Permitting Complete November 2021
Construction Start February 2022
Construction Complete July 2022

 

PUBLIC NOTICE

Utility Construction and Paving on N. Pacific, 4th Av, Oak St, and 5th Av

Construction to replace old sewer lines, water lines, and storm drains, and to repave the N. Pacific from Allen to Cowlitz Way, 4th and 5th from Oak to Allen, and Oak from 4th to 5th will begin in mid-February 2022 and continue into June or July, depending on weather. In addition to the paving and utility work, sidewalk access ramps will be replaced at most of the corners to bring them into compliance with the federal “Americans With Disabilities Act” requirements.

During construction, driveways, travel lanes and parking on these streets will be closed at times, and traffic will be shifted around the construction with traffic cones and flaggers, or will be detoured.

Funding for the project is provided by the City, and by a grant from the Transportation Improvement Board.

City of Kelso
Engineering Department
360-423-6590